Jun 10th, 2020Steam drum lifting was completed.
-
Feb 28th, 2020Ceremony Held to Commemorate Erection of Boiler Frame
-
Jan 31st, 2020Construction of Fuel Tank Wall Foundations Completed
-
Nov 30th, 2019Construction of the Turbine Structure Progressing
-
Oct 31st, 2019Fuel Tank Installation Work Commenced
-
Aug 31st, 2019Construction of Fuel Tank Concrete Wall Foundations Completed
-
May 31st, 2019Construction of Fuel Tank Foundations Progressing
-
Apr 30th, 2019Concrete Poured for Fuel Tank Base
-
Mar 31st, 2019Construction of Fuel Tanks Progressing
-
Jan 31st, 2019Fixed-Point Observation of Entire Kanda Biomass Site Commenced