Jun 10th, 2020

Steam drum lifting was completed.

 

The steam drum which arrived at the power plant in the middle of April was lifted and installed to the boiler.

(the steam drum is an important piece of equipment to separate steam and water from the heat generated by the combustion of fuel in the boiler to make hot water containing steam)

Kanda Biomass Under Construction