Quang Tri Onshore Wind

Apr 27th, 2021

Wind turbine assembly finally started

Since the commencement of construction in May 2020, the Projects have proceeded through earthworks and foundation work,  and are now starting wind turbine assembly work.
Construction of transmission lines inside and outside the project site, as well as substations, is also under way.

We will continue the construction, with safety as always the top priority, aiming for completion in October .

 

Aerial view of completed nacelle installation

 

Lifting the tower section(15.84m in length, weight 88 tons)

 

Using a 600 ton crane to install the tower

 

Onshore Wind Vietnam Under Construction